ONGOING PROJECTS
SUGEE SRUSHTI
Dadar (E)
MahaRERA: P51900077195
Configuration: 2 Bed
Current Status: Demolition in Progress
SUGEE SAMRUDDHI
Dadar (W)
MahaRERA: P51900056033
Configuration: 3 & 4 Bed
Current Status: Plinth Completed
SUGEE VIJAYSHREE
Dadar (W)
MahaRERA: P51900052518
Configuration: 3 Bed
Current Status: Slab 11
SUGEE SUKRUT
Dadar (W)
MahaRERA: P51900051181
Configuration: 2 Bed
Current Status: Slab 14
SUGEE SHRADDHA
Dadar (W)
MahaRERA: P51900032594
Configuration: 1, 2 & 3 Bed
Current Status: Nearing Possession
SUGEE RENAISSANCE
Girgaum
MahaRERA: P51900051597
Configuration: 2 & 3 Bed
Current Status: Slab 15
SARASWATI NIWAS
Dadar (W)
MahaRERA: P51900048130
Configuration: 3 Bed
Current Status: Slab 22
SUGEE AKANKSHA
Dadar (W)
MahaRERA: P51900027981
Configuration: 1 & 2 Bed
Current Status: Terrace Slab
SUGEE INDIRA NIWAS
Dadar (W)
MahaRERA: P51900048976
Configuration: 3 Bed
Current Status: Slab 21
SUGEE TATHASTU
Dadar (W)
MahaRERA: N/A*
Configuration: 3 Bed
Current Status: Terrace Slab Completed
SUGEE TEAKWOOD
Mulund (W)
MahaRERA: P51800053945
Configuration: 1, 1.5 & 2 Bed
Current Status: Demolition in Progress
SUGEE MARINA BAY
Worli Sea Face
MahaRERA: P51900011592
Configuration: 3 & 4 Bed
Current Status: Slab 38
SUGEE SEA KREST
Worli Sea Face
MahaRERA: P51900051903
Configuration: 4 Bed
Current Status: Piling Work
EMPIRE TOWER
Lamington Road
MahaRERA: P51900077429
Configuration: 3 & 4 Bed
Current Status: Excavation in Progress
CONSTRUCTION UPDATE
Construction update for September 2024, highlighting the significant advancements achieved in each project.
COMPLETED PROJECTS
ATHARVA
Dadar West
Delivered in 2024
SHUBHADA
Dadar West
Delivered in 2023
PAAVAN
Matunga East
Delivered in 2023
MAHALAXMI
Hindu Colony
Delivered in 2022
LAXMI NIWAS
Dadar West
Delivered in 2022
PARIMAL
Dadar West
Delivered in 2022
PREKSHA
Dadar East
Delivered in 2021
SANSKRUTI
Dadar West
Delivered in 2021
GANESH NIWAS
Sion West
Delivered in 2020
GOVIND SADAN
Near Chhatrapati Shivaji Maharaj Park
Delivered in 2020
OM SAT
Matunga East
Delivered in 2019
TRIMURTI
Dadar West
Delivered in 2018
SUGEE SADAN
Dadar West
Delivered in 2017
HIRANYA
Dadar West
Delivered in 2015
SUGEE HEIGHTS
Mulund
Delivered On Time
VAIBHAV APARTMENTS
Dadar West
Delivered On Time
VAIBHAV CHAMBERS
BKC, Bandra
Delivered On Time
SHIV SHAKTI
Mulund
Delivered On Time